1. Php 1.8 Bn Bonifacio Global City to Ortigas Center Road Link Project , Phase I, IIA & IIB
STATUS: ON-GOING CONSTRUCTION
The full 1.367-kilometer BGC-Ortigas Road Link Project, including the Lawton Avenue – Global City Viaduct, is expected to be completed by September 2021. Once finished, DPWH said that the project would reduce travel time between BGC and Ortigas Center from a one-hour trip to 12 minutes.
2. Php 10.4 Bn Circumferential Road 3 (C3) Missing Link Project
STATUS: FOR NEDA BOARD APPROVAL
Alex Bote, director of DPWH Public-Private Partnership Service, said the planned 8.6-kilometer C3 Expressway that would pass the Ayala central business district and connect cities of Manila, Makati, and Pasay, would have a conflict in terms of alignment with the C3 Missing Link Project.